Stearns Renovation Project Schedule

This schedule is subject to revision. Please check back periodically for any updates.

December 2007 - Late February 2008

Construction in Dewey, Governor's, Senator's and SHAPE will begin. Offices and functions will be moved as the spaces become available.

Mid-March 2008

Work in Dewey will be completed and preparations in Stearns will begin.

April 2008

Demolition in Stearns will begin over Spring Break.

Late May 2008

Demolition on levels three and four will begin immediately following Commencement (May 17, 2008)

Fall Semester 2008

The new dining room and kitchen will be operational before the start of the fall 2008 semester

November 2008

Project completed