Stearns Renovation Project Schedule
This schedule is subject to revision. Please check back periodically for any updates.
December 2007 - Late February 2008
Construction in Dewey, Governor's, Senator's and SHAPE will begin. Offices and functions will be moved as the spaces become available.
Mid-March 2008
Work in Dewey will be completed and preparations in Stearns will begin.
April 2008
Demolition in Stearns will begin over Spring Break.
Late May 2008
Demolition on levels three and four will begin immediately following Commencement (May 17, 2008)
Fall Semester 2008
The new dining room and kitchen will be operational before the start of the fall 2008 semester
November 2008
Project completed